How long can a commercial permit take in South Florida in 2026?
For a nonresidential building under 25,000 SF, Florida law gives the local government 60 business days from a complete application to approve or deny. If it misses that deadline, the permit fee is reduced 10% for each business day late. ClearBuild's permit model puts typical tenant-improvement reviews at roughly 3 to 12 weeks depending on the city (field estimates, not guarantees).
Source: Fla. Stat. §553.792 · ClearBuild permit model (ClearBuild South Florida field research)